How to Manage an Individual Resource Calendar

ConceptDraw PROJECT Server allows tracking the most important aspects of managing a project, including scheduling, and resource management. Project resources are any people, equipment, or materials needed to complete tasks in a project. Knowing what resources are engaged in the project and keeping communications with people resources will help you in an adjustment of your project from beginning to completion. While ConceptDraw PROJECT Server provides you with default calendar (Monday-Friday; 8 AM-5 PM), it might not be suitable for some specific resources. You can modify a default calendar to set the specific working time for particular resources. Using individual calendar make easy work on accounting vacations, work in shifts and processes that require using a piece of equipment that can be used in a continuous cycle including nights and weekends.

  1. Open ConceptDraw PROJECT Server. The Projects page will be opened by default.
  2. Select a workspace and click the desired project title. The selected project will be opened in the Gantt chart view.
  3. Open the Settings tab. On the right side of the page, you can see the project and resource calendars. In the list you can select calendar you want to modify.

  4. how-to-manage-resource-calendar

  5. Select the date you need to change.

  6. how-to-manage-resource-calendar

  7. A calendar change is available for one specific day, as well as for the day of the week. By switching the EDIT MODE you can distribute changes to the entire schedule. For example, to all Fridays within the current Workspace.

  8. how-to-manage-resource-calendar

  9. You can make the whole day nonworking using the DAY IS switch.

  10. how-to-manage-resource-calendar

  11. You can change the working hours.

  12. how-to-manage-resource-calendar

  13. Confirm your changes by clicking the SAVE button.
How to Manage an Individual Resource Calendar *

How it works:

  • Upload up to 100 project easily
  • Simple tracking of multiple projects status
  • Effective collaboration with project team
  • View and analyze project implementation online

ConceptDraw OFFICE:

ConceptDraw DIAGRAM
  • Business diagramming on Mac OS® and Windows®
  • Compatibility with MS Visio®
  • Live Objects technology

ConceptDraw MINDMAP
  • Compatibility with MindJet MindManager®
  • Import/Export data from MS Project®
  • Integration with Twitter®
  • Collaboration via Evernote®

ConceptDraw PROJECT
  • Compatibility with MS Project®
  • Import/Export data from MS Excel®
  • Import/Export data from MindJet MindManager®
  • Manage multiple projects from a single file

Products

  • ConceptDraw OFFICE v11
  • ConceptDraw DIAGRAM v18
  • ConceptDraw MINDMAP v16
  • ConceptDraw PROJECT v15
  • ConceptDraw STORE
  • ConceptDraw BOOKS

Solutions

  • Free
  • Premium

Samples

Support

  • Technical Support
  • Upgrade Request
  • Visio File Conversion
  • System Requirements
  • Helpdesk
  • Students & Educators
  • Enterprise
  • Customer Service

Solutions

  • Free
  • Premium

Samples

Video Room

  • Products
  • Solutions

Ready To Buy

  • Buy Online
  • Reseller Partners
  • Manage Your Account
  • Download Your Software
  • CS Odessa

    • About Us
    • Contact Us
    • CS Odessa Identity
    • News
  • CS Odessa
    Plan. Do. Communicate.

    About Us | Contact Us | Feedback | EULA | Privacy | TOU | TOS
    © 1993 — 2025 CS Odessa Corp.