Managing Resources

There are two types of resources: human and material. Human resources are those normally in charge for task completion and task executors; material resources depend on the character of the task. It can be equipment, various materials (print, construction etc.), transport, food etc.
To work with resources, first of all you need to switch to Resource Sheet view (use Resource Sheet in menu View).

Making up and editing Resource Sheet

Adding new resources or editing the already existing ones can be done in dialog Resources. This dialog can be called by the following ways:

  1. To add a new resource:
    1. Use Add Resource in menu Workspace
    2. Use button Add Resource on the toolbar Workspace.
    3. Call the context menu and use Add Resource.
  2. To edit the existing resource:
    1. Use Edit Resource in menu Workspace
    2. Use button Edit Resource on the toolbar Workspace
    3. Call the context menu and use Edit Resource
    4. Double-click on the resource
Edit Resource. PC
Edit Resource. MAC

 

In the dialog the following data is specified:

  • Resource name
  • Resource type (human or material). To specify a resource type double-click on the cell with resource type, press the arrow on the right and select the needed type.
Resource type. PC Resource type. MAC
  • Cost
  • E-mail address (for workers)
  • Notes on resource

In the pop up list on the right, select a period for which payment is done: hour, day, week or month.

Hour, day, week or month. PC Hour, day, week or month. MAC

 

Closing the dialog, do not forget to press OK to save changes.

Note: resources can be copied/ cut and then pasted to the needed place. For this use Copy / Cut / Paste in menu Edit. For quick selection of all the resources simultaneously use Select All in menu Edit.

To delete a resource:

  1. Use Delete Resource in menu Workspace.
  2. Use button Delete Resource on the toolbar Workspace.
  3. Call the context menu and use Delete Resource.

Task: In our example, let’s add one more worker - the second assistant and two material resources - equipment and transport.

 

Assigning resources to tasks

Assigning resources to tasks or editing the already assigned resources can be done in dialog Task Information on tab Resources. This dialog can be called by one of the following steps:

  1. Use Assign Resources to Task in menu Tasks.
  2. Select Assign Resources to Task in the task context menu.
  3. Use button Assign Resources to Task on the toolbar Tasks.

Check resources you want to assign to a task In column Type resource type can be changed, and in column Units you can specify the degree of resource occupancy in the given task (for human resources - in percent, for material - in appropriate units). If at completing a task a worker is fully occupied in it, i.e. he/she is currently not involved in any other task; his/her occupancy degree is 100%.

Task Information: Resources. PC
Task Information: Resources. MAC

 

Closing the dialog, do not forget to press OK, to save changes.

After assigning resources to tasks resource names will be shown in Gantt Chart (next to the bar representing the task).

Task: In our example, let’s assign resources to the tasks "Find out about the equipment on hand and the equipment to buy", "Hire a bus to take people there and back", "Buy food", and "Buy lacking equipment" using all the 3 methods of assigning resources.

Exm: Using all the 3 methods of assigning resources