Calls Edit Calendar Dialog |
 |
Calls Workspace Properties
dialog that allows to customize working days and hours during all workspace
projects time |
 |
Creates a new project within the given workspace. Change
Project Properties dialog will appear to customize project parameters |
 |
Calls Change Project Properties
dialog for selected project |
 |
Removes selected project(s) |
 |
Calls Reports dialog that allows
to generate reports on workspace state |
 |
Creates a new resource. Resource
dialog will be called for customizing resource parameters |
 |
Calls Resource dialog for selected
resource |
 |
Removes selected resource(s) |
 |
Creates finish-to-start dependency between selected task. The
link arrow will be directed to the task selected first |
 |
Removes dependency between selected tasks |