Content | Reference
Context menu of Gantt chart task list
This menu can be started from the window of Gantt chart task list:
by clicking the right
mouse button
by clicking the mouse
button and Control
In this menu all commands for work with tasks are collected:

Insert New Task - Inserts a task before the selected one. If no task is selected, inserts a task atfer the last one in the project
Add New Subtask - Inserts a subtask for the selected task
Append Task - Appends a task to the end of task list
Delete Task(s) - Removes selected task(s)
Move Up - Moves the selected task one step up
Move Down - Moves the selected task one step down
Indent - Moves the selected task one level deeper
Outdent - Moves the selected task one level closer to the root
Show Subtasks - Unfolds the subtasks of the selected task
Hide Subtasks - Folds up subtasks of the selected task
Show All Subtasks - Shows all subtasks in the project
Hide All Subtasks - Hides all subtasks in the project (shows only project phases and tasks of the same level)
Go To Selected Tasks - Scrolls horizontally graphic part of Gantt Chart so that the time bar of the selected task is seen on the screen
Milestone - Converts the selected task into a milesone if
it has not been one before. Otherwise milestone status will be removed. If the
selected task is a milestone, this command is marked in the menu
Deadline - Specifies a deadline for the selected task if
it has not had it before. Otherwise the deadline will be removed from the task.
The deadline will coincide with the task Finish Date. To specify another time
for the deadline call Task Information
dialog. If the selected task has a deadline, this command is marked in the menu
Task Information… - Calls Task
Information dialog for the selected task.
Assign Resource(s) To Task… - Allows to assign resources for the selected task. Task Information dialog with opened Resources tab will appear for it
Predecessors… - Calls Task
Information dialog for the selected task on the tab Predecessors.
You can create various types of intertask dependencies for the task here
Task Notes… - Calls Task
Information dialog for the selected task on the tab Notes.
Note for the task can be added here
Link Tasks
- Assign link 'finish to start' to the selected tasks
Unlink Tasks - remove links from the selected tasks
Send EMail To
Assigned Resources - send a letter by
e-mail to the human resources involved in the given task
Many tasks from this menu are available from the menu Tasks
and on the tollbar Tasks.
Content | Reference
|